Chapter 3 Installing the Library
Setting Up and Testing the Library
24 ACL 4/52 Facilities Planning and Installation Guide
Setting Up and Testing the Library
3
The following procedures verify the proper operation of the ACL 4/52
library:
Turning on the library
Setting SCSI addresses
Configuring library options
Running a system test
Performing an inventory
Turning On the
Library
3
To turn on the library:
1 Verify the following:
Actuators move freely in the horizontal and vertical directions
All doors are closed
All cosmetic panels are attached
Power switch in the
O
(off) position
Caution:
Using a digital voltmeter (DVM), verify that the facility
power is
90-132VAC or 180-264 VAC @ 47-63Hz before connecting
the AC power cord.
2 Connect the AC power cord to the rear panel and facility power.
3 On the rear panel, set the power switch to the “|” (on) position.
4 After several seconds, verify that the control panel displays library
status.
Setting SCSI Addresses
3
After power is applied to the library, you need to set library and tape
drive SCSI addresses. Setting SCSI addresses require operator- or
service-level security clearance at the library control panel.
Configuring Library
Options
3
In addition, you may want to change the default configuration (in
bold) of these options:
Library power-up state (online/offline)